Jump to: navigation, search

Master Schedule Overtime Requirement: Options Dialog Box

Use the Options dialog box to specify the columns that the Master Schedule Overtime Requirement view displays.

  1. Click the Options button WM 851 icon-options.png on the Master Schedule Overtime Requirement view's Actions toolbar.
    The Options dialog box opens. Only the Overtime Scheduled check box is selected by default.  
  2. Select the check boxes for the column(s) that you want to be included in the display:
    • Overtime Scheduled
    • Staffing Calculated
    • Staffing Required
    • Staffing Coverage
    • Staffing Variance
    • Difference Calculated
    • Difference Required
  3. Click OK to apply your choices.

Feedback

Comment on this article:

blog comments powered by Disqus