The data in iWD Data Mart is made available through a process that is called Extract, Transform and Load—or ETL, for short. The system that is used to create, configure, and execute the ETL process is Kettle, which is part of the Pentaho reporting suite. Kettle top-level objects are known as jobs. Jobs are a sequence of steps that are executed according to success/failure criteria. One of the steps that is used by iWD reporting is to transform steps.

The following list describes the preconfigured ETL jobs that are responsible for creating and populating the iWD Data Mart and for calculating the various aggregates and dimensions that are described in the iWD Data Mart schema. Jobs names are those displayed in iWD GAX Plugin's Data Mart Dashboard.

Preconfigured ETL Jobs
Job Function Attribute Description
Initialize iWD Data Job Name Initialize
Function Initializes the necessary data structures and populates static dimensions, such as the AGE, BUSINESS_VALUE, EVENT_DATE, EVENT_TIME, DATE_TIME, PRIORITY, STATUS, TASK_EVENT_TYPE, and TIMEZONE dimensions.
Schedule Runs once.
Load Configuration Job Name Load Configuration
Function Loads iWD configuration updates from the following ETL parameters:
  • customTaskAttributeMapping
  • customTaskDimensionMapping
  • customTenantAttributeMapping
  • customDepartmentAttributeMapping
  • customProcessMapping

into the ETL_CUSTOM_MAP and CUSTOM_DIM Data Mart tables. This function loads iWD configuration updates that have been gathered from the configuration database into the following Data Mart tables:

Schedule Configurable through service properties; typically, runs on a 15-minute cycle, but not more frequently than a 15-minute cycle.
Load Intraday Job Name Load Intraday
Function Loads updates from tables in the Interaction Server database and event log into the following core fact tables:

as well as the following dimensions:

Schedule Configurable through Service Properties in iWD GAX Plug-in; recommended that it be scheduled to run after the Load Configuration job ends through the Job Dependency scheduling option.
Aggregate Intraday Job Name Aggregate Intraday
Function Aggregates data that previously was loaded into fact tables by the Load Intraday job into the aggregation tables.
Schedule It is recommended that this job be scheduled immediately after the Load Intraday job has completed—typically, running every 15 minutes. The frequency of running this aggregate job does not have any bearing on the current 15-minute aggregate that is being populated.
Aggregate Statistics Job Name Aggregate Statistics
Function Generate extended statistics by executing statistics plug-ins.
Schedule It is recommended that this job be scheduled immediately following completion of the Aggregate Intraday job, because most of the statistics plug-ins user aggregated facts.
Load GIM Job Name Load GIM
Enabling You can enable this job by setting the option gim-load-enabled to true. This option is located in the [settings] section of iWD Runtime Node application. You must also add Genesys Info Mart (GIM) DAP to the Connections tab of iWD Runtime Node application. See Enabling or disabling Load GIM job.
Function Loads data from the RESOURCE_ table in the GIM Database into the RESOURCE_ table in Data Mart.
Schedule Configurable through the Service Properties in iWD GAX Plug-in; recommended that it be scheduled to run at the end of execution chain after the Stat Adapter Job.
Load Historical Job Name Load Historical
Function Moves noncurrent data from the intraday fact tables to their corresponding historical fact tables. (“Noncurrent” refers to data other than today’s data [CREATED_DATE_KEY < today].)
  • Noncurrent I_TASK_EVENT_FACT data is moved to H_TASK_EVENT_FACT.
  • Noncurrent I_TASK_WORK_FACT data is moved to H_TASK_WORK_FACT.
  • Noncurrent I_TASK_FACT data is moved to H_TASK_FACT.
  • (Only in release 9.0.013.xx or lower) Noncurrent I_TASK_aggr_FACT_15min data is moved to H_TASK_aggr_FACT_15min.
Important
  • Task facts must also be finalized (having reached Completed, Canceled, or Rejected state) before they can be moved from the intraday fact tables regardless of duration in the intraday tables.
  • Starting from the release 9.0.014.xx, the I_TASK_aggr_FACT_15min aggregation tables (for standard aggregation plugins: agent, capture, classification, queue, age) are removed from the iWD Data Mart schema.
Schedule Runs daily through the schedule that is defined in Service Properties.
Aggregate Historical Job Name Aggregate Historical
Function Aggregates data for the historical DAY aggregation tables (H_TASK_aggr_FACT_DAY).
Schedule Runs once a day, after the Load Historical job.
Maintain iWD Job Name Maintain
Function Removes expired facts based on the Record Details value under Expirations tab in Data Mart configuration from the following tables :
  • H_TASK_EVENT_FACT
  • H_TASK_WORK_FACT
  • H_TASK_FACT

Removes the expired aggregated facts based on the Aggregation 15 min value under Expirations tab in Data Mart configuration from the following table:

  • H_TASK_aggr_FACT_15min if the Aggregate Historical Job has processed data for this period

(These parameters are defined as rules on the ETL Service property in iWD GAX Plug-in.) This job also adds to DATE_TIME ensuring that next-year values are present in this table.

Schedule Runs once a day, after the Aggregate Historical job.

You can schedule ETL jobs to run:

  • On a recurring basis by using a CRON expression.
  • Manually.
  • Upon the successful completion of a dependent service.

For more information on the configuration of scheduling ETL jobs, refer to the iWD 9.x Deployment Guide.