This page was last edited on May 31, 2024, at 08:42.
Comments or questions about this documentation? Contact us for support!
You can start and stop Genesys Mobile Services in the following ways:
Objective | Related procedures and actions |
---|---|
Using Solution Control Interface (SCI) | Complete the following procedure: |
Using Genesys Administrator | Complete the following procedure: |
Prerequisites
Start
End
For information about how to use SCI, refer to Framework Solution Control Interface Help.
Prerequisites
Start
End
When you select a graceful shutdown, the Solution Control Server (SCS) sends a suspend message to GMS, so that GMS sets itself to OFFLINE. Load Balancer will no longer send requests to this GMS. After a configurable delay, SCS sends a STOP signal, and the GMS will stop. To configure this delay:
Start
End